Work to Begin Tonight on HBC Fiber Relocation Project

For Immediate Release (10/23/2018)

Winona, MN –  The work of transferring HBC customers to a new fiber-optic cable will begin tonight. The work is required to facilitate redevelopment of the former Hardee’s block. HBC has two fiber trunk lines buried in the block which must be relocated.

Moving those fiber lines will involve the cutting and individually re-splicing thousands of tiny fiber-optic strands, which are about the size of a human hair. HBC Field Operations Manager, Dan Fortek, said work will occur the next two nights beginning at 12:30 am and continuing until around 4:00 am. HBC Customers living east of Main Street will be the only Customers affected by this work.

“We will be conducting the cut-overs as seamlessly as possible in an effort to minimize service outages,” Fortek said. “We will have two teams of technicians working both nights in order to have services reconnected as quickly as possible. Customers can expect their services to be down between a half-hour up to 45 minutes.”

The entire relocation project is expected to be completed by 5:00 Wednesday morning.