10/20/2021

We are pleased to announce that services are now available in PON A!

Fiber splicing will be completed by the end of the week in PON E with testing to begin Monday. If all goes well, services will be available in PON E by the end of next week.

Fiber splicing is completed in PON A and network testing is happening this week. Services should be available on Monday, October 18th!

If you live in PONs A and E and have not already done so, please click here to arrange for your service drop pre-bury today! This will make your home ready to receive service as soon as construction is completed in your neighborhood. Then call our local Hastings office at (855) 804-4031 and one of our local Customer Care Representatives will be happy to sign you up for services.

Drop pre-buries and pre-bury site specs are continuing throughout PONs A and B.

Conduit boring continues in PON C with two crews working in the area this week. Work will be focused on Northridge Drive, Timberview Drive, and Graystone Road.

To learn more about HBC services, receive construction project updates, or sign up for services, please visit hbci.com/hastings. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

If you have any questions about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you as a customer and a friend!

The Ochs’ kids with the HBC truck.

The Ochs’ kids with the HBC truck.

10/13/2021

Our service technicians are staying busy with installations in PON B this week! Congratulations to the Ochs family on being the first HBC customers in Hastings! Their kids look pretty excited about getting connected to our super-fast fiber-optic network!

Fiber splicing is completed in PON A and network testing is happening this week. Services should be available on Monday, October 18th!

If you have not already done so, please click here to arrange for your service drop pre-bury today! This will make your home ready to receive service as soon as construction is completed in your neighborhood. Then call our local Hastings office at (855) 804-4031 and one of our local Customer Care Representatives will be happy to sign you up for services.

Crews continue to bore conduit in PON C. This work will continue for the next several weeks.

Fiber has been pulled in PON E with splicing to begin later this week.

If you would like to learn more about HBC services, receive construction project updates, or sign up for services, please visit hbci.com/hastings. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

If you have any questions about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you as a customer and a friend!

10/07/2021

HBC Splice Cabinet

HBC Splice Cabinet

Great news! HBC Gigabit Internet and Phone services will be available Monday to residences in PON B! The splice cabinet was powered up early this week and final network testing will continue through the remainder of the week.

The push is on to complete splicing this week in PON A with testing expected to occur next week. The estimated date for services in PON A is the week of October 18th.

If you live in PON A or PON B and have not already arranged for your service drop pre-bury, do so today! Visit hbci.com/drop and fill out the form. This will prepare your home for services as soon as construction is complete.

All fiber has been pulled in PON E and splicing crews will begin working there next week.

In PON C, conduit boring was halted after a drill developed mechanical issues. Repairs have been made and crews will be boring conduit along Northdale Drive to Timberview Drive this week.

To learn more about HBC services, receive construction project updates, and to sign up for services, please visit hbci.com/hastings. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

If you have any questions about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you as a customer and a friend!

09/29/2021

We know you are eagerly waiting for HBC broadband services. That long-awaited date is quickly approaching with crews diligently working to complete splicing fiber at the main splice cabinet. A date is being scheduled for Xcel Energy to turn on power to the cabinet that will allow for network testing to be completed and services to be released.

Fiber splicing resumes this week in PON A where work is expected to be completed by the end of next week.

The pace of work in PON C is increasing with two conduit boring crews operating the area this week. Crews will be completing work in the areas of Carlton Drive and Carlton Place and then move towards Northridge Drive as utility locates are completed.

Fiber is being pulled in PON E and should be completed and ready for splicing next week.

Lawn restoration efforts are being stepped up as we hope to get as much grass seed on the ground before the current growing season ends.

Service drop pre-buries will continue throughout the week in PON B. We are optimistic that services could be available for PON B residents by the end of next week.

Please visit hbci.com/hastings where you can learn more about our service offerings, receive updates on construction progress, and sign up for services. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

To begin the process of receiving HBC Internet and Phone service, please click the SIGN UP button on the hbci.com/hastings page to complete the “Drop Burial Authorization Form.” This will make your home ready to receive service as soon as construction is completed in your neighborhood.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you as a customer and a friend!

09/24/2021

All fiber has now been pulled in PON A with splicing currently underway. This work is expected to be completed in the next 10 to 14 days.

All splicing and testing have been completed in PON B.

The construction crew has wrapped up conduit boring in PON E with fiber being pulled there this week.

Boring operations have now moved to PON C where work will continue through at least next week.

Fiber splicing at the splice cabinet is proceeding and will continue into next week. The current timeline has services becoming available the week of October 4th.

The wait to receive services will soon be over and we are excited to have you be part of our HBC family. Please visit hbci.com/hastings where you can learn more about our service offerings, receive updates on construction progress, and sign up for services. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

To begin the process of receiving HBC Internet and Phone service, please click the SIGN UP button on the hbci.com/hastings page to complete the “Drop Burial Authorization Form.” This will make your home ready to receive service as soon as construction is completed in your neighborhood.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

09/15/2021

The last of the fiber in PON A will be pulled this week. Splicing is already underway and will be completed next week followed by a testing period to ensure everything is ready to go for the release of services.

Service drop pre-buries are expected to continue this week in both PONs A and B. Lawn restoration crews will also be working in this area.

Conduit boring in PON E is expected to be completed before the end of the week with work then moving into PON C.

Installation of the cabinet that will route the fiber connecting all PONs to HBC’s fiber-optic network is underway. Work should to be completed over the next two weeks with services expected to be available in PON B in the final week of September.

We are looking forward to having you join our HBC family! Please visit hbci.com/hastings where you can learn more about our service offerings, receive updates on construction progress, and sign up for services. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

To begin the process of receiving HBC Internet and Phone service, please click the SIGN UP button on the hbci.com/hastings page to complete the “Drop Burial Authorization Form.” This will make your home ready to receive service as soon as construction is completed in your neighborhood.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

09/10/2021

The pulling of fiber in PON A will be completed over the next several days with splicing to begin next week.

Service drop pre-buries continue in PON B. This process will transition into PON A in the next few days.

Construction crews plan to begin boring conduit in PON C next.

On Monday, work will begin to install the cabinet that will house the fiber connecting PON B, and all subsequent PONs, to HBC’s fiber-optic network! Splicing and additional testing is expected to take two weeks. We are hoping be connecting customers to the network the final week of September.

We are looking forward to having you join our HBC family! Please visit hbci.com/hastings where you can learn more about our service offerings, receive updates on construction progress, and sign up for services. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

To begin the process of receiving HBC Internet and Phone service, please click the SIGN UP button on the hbci.com/hastings page to complete the “Drop Burial Authorization Form.” This will make your home ready to receive service as soon as construction is completed in your neighborhood.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

09/02/2021

All splicing and testing in PON B is now completed. Service drop pre-buries began this week in PON B in preparation for activation of the network, which we expect to happen in about 3 weeks.

Conduit boring will be completed this week in PON A. Crews have begun pulling fiber and expect to have 90 percent of all fiber in PON A “pulled” by the end of this week, with splicing scheduled to begin on September 13th.

Conduit boring will begin in PONs C and E next week.

We are getting excited as we get closer to activating our state-of-the-art fiber-optic network and we are looking forward to serving our first Hastings customers!

Please visit hbci.com/hastings where you can learn more about our service offerings, receive updates on construction progress, and sign up for services. Click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

To begin the process of receiving HBC Internet and Phone service, please click the SIGN UP button on the hbci.com/hastings page to complete the “Drop Burial Authorization Form.” This will make your home ready to receive service as soon as construction is completed in your neighborhood.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

08/25/2021

This week conduit boring crews will be finishing work in PON A and installing the final pedestals clearing the way for fiber to be pulled. Soon we will begin to bury fiber-optic lines (“drops”) to homes in PON A to those who have requested a drop be buried to their home prior to receiving HBC services. If you are interested in receiving HBC services, but have not yet requested your drop pre-bury, you can find the form here.

In PON B, splicing has been completed and testing is expected to be finished this week. It is anticipated services to this area will be available around mid-September.

We have seen some delays in utility locates in PON C, but expectations are for underground utility locations to be flagged yet this week. Conduit boring in PON C can begin once that work is completed.

PON E will be the next area of construction. Utility locates are expected to begin after Labor Day.

You may visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

08/20/2021

Progress was slowed in PON A by a shortage of available utility locators. Current progress models have conduit boring being completed in the next 7 to 10 days. The placement of service pedestals and vaults is expected to continue in PON A for the next two weeks in preparation for pulling fiber-optic cable. Once boring is finished in PON A, crews will immediately begin working in PON C.

All fiber has been pulled in PON B. Testing of fiber signal strength began Monday morning and is expected to be completed by the end of this week. Lawn restoration crews continue their work in PON B, hydro-seeding lawn areas disturbed by construction. We have started to bury fiber-optic lines (“drops”) to homes in PON B that have requested a drop be buried to their home prior to receiving HBC services. If you are interested in receiving HBC services, but have not yet requested your drop pre-bury, you can find the form here.

A right-of-way discrepancy has delayed the placement of the main service cabinet. This cabinet will serve as the connection point between new construction areas and the existing HBC fiber-optic network. Approval has now been given for placement of the cabinet and this work will begin over the next few days.

Please visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

08/09/2021

PON A Construction Progress

PON A Construction Progress

Significant progress has been made in both PON A and PON B!

Conduit boring in PON A is 50% complete and expectations are to have all conduit in place by the end of next week.

In PON B, fiber splicing has begun. The current timeline calls for all splicing and testing to be completed over the next two weeks.

Recent rains have softened lawns resulting in additional yard damage caused by the drilling rigs. Our contractor is acting to mitigate those instances and perform lawn restoration work.

PON B Construction Progress

PON B Construction Progress

Please visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

07/28/2021

PON A Progress Map

PON A Progress Map

This week, boring will continue in PON A along Tierney Drive. Fiber is being pulled in PON B and crews will begin splicing in preparation for connecting PON B to the network.

Many are asking about the lawn restoration process to repair the areas that were damaged during boring. There are two phases to this process.

Within two weeks of completing a section, a crew will do an initial restoration of the lawn damage. This includes covering the damaged area with black dirt and seeding. Due to the drier conditions, we hope that all homeowners would assist in keeping the seed watered to ensure germination.

The second phase will occur in the fall (September or October depending on the weather), when crews will evaluate previously seeded areas. Any areas found where seed germination was not successful, additional seed will be sowed giving the highest success rate for germination in the spring.

We invite you to visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. You can also stop into our local Hastings office at 1775 Market Blvd. to speak with a Customer Care Representative. We are looking forward to serving you!

07/22/2021

PON A and B Progress Map

PON A and B Progress Map

Work has now begun in PON A. On Monday, crews began boring along Tierney Drive and will proceed westward towards Erickson Drive this week. Our contractor will have two boring drills in operation for the next several days and we are expecting work in PON A to progress quickly! Locators continue to flag underground utilities ahead of construction crews.

In PON B, conduit boring has been completed and the final vaults and pedestals are being installed prior to pulling the fiber-optic cable through the conduit. This will begin later this week. Once the fiber-optic cable is in place, crews will begin splicing the PON B fiber to the main network. Barring any delays, this work could be completed as soon as the first week of August.

Lawn restoration work will continue throughout the week in PON B.

As always, if you have any questions or concerns regarding construction in your neighborhood, please call our Construction Hotline at (651) 432-4357. Also feel free to stop into our newly opened Hastings office located at 1775 Market Blvd. to speak with one of our local HBC Customer Care Representatives!

Visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox.

07/16/2021

Hastings PON B Map

Hastings PON B Map

Crews will be boring conduit along Todd Way and Todd Court this week. This is the final section to complete and will conclude boring operations in PON B. There are several pedestals and vaults that need to be installed and that work will continue for the next week as well.

An unexpected delay in the delivery of a fiber splicing cabinet has caused a minor setback to our completion timeline. Once the cabinet has been installed, fiber will be pulled through the conduit. We are hopeful services will be available in PON B by mid-August.

Once boring is completed in PON B, work will begin immediately in the next area for construction, PON A. Residents in this area should begin seeing utility locators flagging in the street right of way in the coming days.

Visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox. For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. We are looking forward to serving you!

07/09/2021

Hastings Office

HBC Hastings Office

The new HBC local Hastings office is now open and ready to serve you at 1775 Market Blvd. in Hastings!

The office is open Mondays & Thursdays 9:00 a.m. to 6:00 p.m. and Tuesdays, Wednesdays & Fridays 8:00 a.m. to 5:00 p.m.

We invite you to stop by and say “Hello!” Our Customer Care Representatives will be happy to answer questions regarding services and help you get you signed up to receive HBC Gigabit Internet and Phone service when they become available in your neighborhood.

HBC Wizards Technical Support is available 7 days a week, 24 hours a day by calling (877) 457-9669. The Hastings office will soon have a HBC Wizards Technician on site to assist with any technical needs.

We invite you to visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox. For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. We are looking forward to serving you!

07/01/2021

July Construction Progress

July Chatfield PON B Construction Progress

Steady progress continues to be made each week, despite running into some more areas of rock, 2,009 feet of conduit is now in place. Our contractor estimates that nearly three-quarters of PON B (the first section to be constructed) has the necessary conduit in place! This week construction will be focused on Brittany Road, Tierney Drive, and Tierney Court over to Todd Way.

As construction progresses, more locator flags will be placed in preparation for the last push of construction in PON B. Contractors will also be focusing on lawn restoration work in areas where construction has been completed. This will include placing dirt and grass seed in the areas where yards were disrupted during construction. These areas will be monitored to ensure the grass is germinating properly.

The current timeline has all conduit being placed by mid-July, at which time the pulling and splicing of the fiber-optic cable will begin. Provided there are no delays, residents of PON B could be able to receive services in early August!

We invite you to visit hbci.com/hastings to learn more about our service offerings. While you are there, be sure to click the STAY INFORMED button and complete the online form to have construction and service updates delivered directly to your email inbox. For any questions you may have about the construction process, please call our construction hotline at (651) 432-4357. We are looking forward to serving you!

06/23/2021

Pedestal being staged for installation.

Pedestal being staged for installation.

Construction progress was slowed last week as crews ran into areas of rock, but they still managed to bury 1,800 feet of conduit. To date nearly 26,500 feet of conduit has been placed.

Boring operations have been completed on Honeysuckle Lane, Blueberry Lane, and Blueberry Court, and along Pleasant Drive between 12th Street W. and 15th Street W. Boring is also finished on 12th Street W. from Honeysuckle Lane west to Christa McAuliffe Elementary School and a short section of 14th Street W. just west of Honeysuckle Lane.

This week, construction will be focused along 14th Street W. to Pleasant Drive and from Brittany Road to Tiereny Court. Crews will also continue to install peds and vaults in areas where conduit has already been buried so they can begin pulling fiber cable through the conduit. Lawn restoration work is underway in those areas where construction has been completed.

If you have any questions regarding the construction process, please feel free to call our local construction hotline at (651) 432-4357. Visit hbci.com/hastings for more information about HBC services that will be coming to you soon! Click the STAY INFORMED button and fill out the form to have construction and service updates delivered directly to your email inbox!

06/16/2021

Construction Crews

Construction workers use a soil compactor to prepare the site of a pedestal installation for lawn restoration.

Good progress was made as construction crews were able to bore and bury several thousand feet of conduit and place multiple vaults and pedestals last week.

Boring operations continued along 12th Street W. towards Christa McAuliffe Elementary School with another 2,700 feet of conduit now in place! On Honeysuckle Lane, boring has been completed, conduit has been placed, and vaults and pedestals are beginning to be installed in preparation for the pulling of fiber.

We are also making progress on our new Hastings office location! The local HBC Hastings office will be located at 1775 Market Blvd. It’s been exciting as furniture begins to arrive and the office layout begins to take shape. The office is scheduled to open on July 1st!

If you ever have any questions regarding the construction process, please call our local construction hotline at (651) 432-4357. Visit hbci.com/hastings for more information about HBC services that will be coming to you soon! Click the STAY INFORMED button and fill out the form to have construction and service updates delivered directly to your email inbox!

06/11/2021

Construction has started and crews have made good progress last week! Around 2000 feet of conduit has been put in place along Honeysuckle Lane from 14th St. W to 12th St. W. This week, construction efforts focused on boring operations on 12th St. W. from Honeysuckle Lane up to Christa McAuliffe Elementary School.

Vault placementCrews have also been burying vaults and placing pedestals as the next steps before fiber-optic cable is pulled through conduit and splicing operations begin. The photo shows construction crews burying an underground fiber vault along Honeysuckle Lane.

We’ll have another project update next week!

If you have any questions regarding the construction process, please call our local construction hotline at (651) 432-4357. Visit hbci.com/hastings for more information about HBC services that will be coming to you soon! Click the STAY INFORMED button and fill out the form to have construction and service updates delivered directly to your email inbox!

05/27/2021

Utility locates have been completed! While we had hopes of beginning construction today, May 27th, the rain has pushed the start of construction to Tuesday, June 1st.  The first area to be built is roughly bordered by South Frontage Road, Pleasant Drive, 15th Street West and Todd Way (yellow area in the image).

The construction process involves boring a pathway underground where a conduit will be placed.  Fiber-optic cable will be put inside the conduit to protect the fiber cabling from moisture which would otherwise be damaged over time. Boring is more efficient and less disruptive than digging a trench to bury conduit.

While work will be done within the street right-of-way, boring may cause minor damage to landscaping in the area where the bore bit enters the ground and where it exits.  Our crew will take the time to repair this damage upon completion of the project.

If you have any questions about the construction process, please call our local construction hotline at (651) 432-4357. Visit hbci.com/hastings for more information about HBC services that will be coming to you soon! Click the STAY INFORMED button and fill out the form to have construction and service updates delivered directly to your email inbox!

05/12/2021

Construction plans have been submitted to the City of Hastings and are currently under review. We hope to receive final approval soon! Once approved, our locator crews will be flagging existing underground utilities, like water and gas lines and other buried services, in preparation for the start of construction.

The tentative construction start date is mid-May with the first homes expected to be ready to receive HBC services in July. If you are interested in learning more about our Internet and Phone services or would like to be one of the first on your street to get service, please visit hbci.com/hastings and simply select the SIGN UP TODAY button. This will allow us to provide you with timely updates on construction progress and let you know when services will be available for your home.

Remodeling of our local Hastings Customer Care office in the Hastings Marketplace is also underway! We hope to be ready to serve you in person July 1st!

If you have any questions or concerns, please call us at (651) 432-4357 or visit hbci.com/hastings for updates and additional information about HBC services.

We look forward to serving you!

04/12/2021

Hastings, MN – Hiawatha Broadband Communications, Inc. (HBC) has announced plans to begin building a fiber-to-the-home (FTTH) network in Hastings, MN that will be capable of delivering speeds of 5 Gigabit. Officials at HBC said they hope to begin construction on a main fiber trunk line as early as mid-April.

HBC currently has a presence in Hastings, providing high-speed Internet to local industry. HBC president Dan Pecarina said the company will be expanding its footprint to include residential customers.

“We are really excited to be able to bring our high-speed broadband service to the residents of Hastings,” Pecarina said. “The FTTH network we’ll be building will employ the latest technology allowing for speeds up to 5 Gigabits. We believe allowing customers to have access to higher symmetrical speeds is crucial because the way we work, learn, and watch television continues to evolve.”

According to HBC Director of Technical Operations, Michael Barker, the project will begin by constructing a transport route on 15th Street from Pine Street west to General Sieben Drive. He said residents should expect to see contractors working in that area relatively soon.

“Residents should start seeing our people begin to mark underground utilities like communications lines, gas, water, and sewer, that are located in the city right-of-way,” said Barker. “We are hoping to begin constructing the transport route by the middle of April, providing we aren’t delayed by weather.”

Barker said once the trunk line is constructed, HBC will start building the fiber network. He said the first area to be built will in the area north of 15th Street W., east of Tierney Park.  Barker estimates that construction will begin sometime in late April or early May.

According to Pecarina, HBC will also have a local Customer Care office in Hastings.

“We have secured an office space located in the Hastings Marketplace,” said Pecarina. “Our hope is to have the office ready to open in June.”